PROJECT COST CONTROL IN THE NIGERIAN CONSTRUCTION INDUSTRY (A CASE STUDY OF EL-ALAN CONSTRUCTION COMPANY (NIGERIA) LIMITED)

PROJECT MANAGEMENT UNDERGRADUATE PROJECT TOPICS, RESEARCH WORKS AND MATERIALS

160 people found this post useful


CHAPTER ONE

INTRODUCTION

Background of the study

Project cost controls in the Nigerian construction sector have always been under studied. On the course of prosecuting a project, controlling the cost of these projects would help in maintaining such projects from being too capital intensive which may lead to the project being abandoned. For every project to be successfully executed, its cost must have been analyzed and the cost from start to finish noted so as to prevent unnecessary contingency spendings which may hamper the complete execution of the project. Cost control includes monitoring cost, task completion, and time. If total cost of a project at a given time is over the cost baseline, cost control measures may be necessary. Such project management actions may range from ensuring that only tasks within the scope of the work are being performed to alerting stakeholders of potential cost overruns. As a project manager, it is important, professional, and ethical to identify and report on these issues as soon as they are identified.

Organizations whether private or government owned must complete projects on budget to achieve financial objectives and save cost. Project managers applying cost control techniques effectively can ensure that projects stay within projected budgets or are allowed to exceed budgets in a controlled way for specific reasons. When an organization implements appropriate project cost controls, it reduces risk and receives the full benefits anticipated from project completion.

Controlling costs means meeting a budget that is based on cost estimates. The two components of such estimates are the scope of the work and the cost of each completed task. The project plan details the requirements for the project, which you have to translate into activities. A typical activity requires labor, materials and equipment. Once you have defined the project scope in terms of activities and divided the activity into its cost components, you can calculate cost estimates using costs from historical sources, bids, industry norms and other projects as a base.

Statement of the general problem

The increase in the number of abandoned, uncompleted and under completed projects by individuals, companies and even government has been a cause for serious concern. This high rate of abandonment has inflicted our infrastructural development negatively and may have dissuadedprospective investors from investing in our economy.

Aims and objectives of the study

The following will be our aims and objectives for undertaking this study

  • To examine the level of implementation of project cost control in the Nigerian construction industry.
  • To know if adherence to project cost control increases the profitability of Nigerian construction industry.
  • To know if project cost control improves the Nigerian construction industry.
  • To know if project cost control reduces abandonment and under completion of projects.

Significance of the study

This study will be of great importance to project managers, government, researchers and captains of industries seeing that it would unravel the implications and benefits of ensuring project cost control in the Nigerian construction industry and the economy of Nigeria at large.

Scope of the study

This study is restricted to project cost control in the Nigerian construction industry with EL-ALAN Construction Company (Nigeria) Limited as its case study.

Limitation of the study

Financial constraint- Insufficient fund tends to impede the efficiency of the researcher in sourcing for the relevant materials, literature or information and in the process of data collection (internet, questionnaire and interview).

Time constraint- The researcher will simultaneously engage in this study with other academic work. This consequently will cut down on the time devoted for the research work.

Research Questions

  • What is the impact of project cost control on the Nigerian construction industry?
  • Does project cost control enhance the quality of constructions in the Nigerian construction industry?
  • What is the impact of project cost control on the infrastructural development of Nigeria?
  • Is there a relationship between project cost control and economic development in Nigeria?

Research Hypothesis

H0: Effective project cost control does not improve the quality of constructions in the Nigerian construction industry

H1: Effective project cost control does not improve the quality of constructions in the Nigerian construction industry

Definition of terms

  • Project:A planned piece of work that is designed to find information about something, to produce something new, or to improve something.
  • Cost:the amount of money that you need in other to buy, make or do something.
  • Construction:the process or method of building or making something, especially roads, building, bridges etc.

 

REFERENCES

Aibinu, A.A. and Jagboro, G.O. (2002) The Effects of Construction Delays on Projects delivery in the Nigerian Construction Industry. International Journal of Project Management 20, 593 – 599

Asamoah, J. (2002) Satisfying the Energy Hunger in West Africa: A Progress on West Africa Gas Pipeline. African energy, Brooke Patrick Publications, Johannesburg, http//www.africanenergy.co.za

Buhari I.B. (1991) Inflation and the Nigerian economy.The Nigerian Quantity Surveyor.8-9 4.

Get the complete project »

OTHER SIMILAR PROJECT MANAGEMENT PROJECTS AND MATERIALS

CAUSES OF CONSTRUCTION PROJECT FAILURES AND ABANDONEMTS IN NIGERIA

 Format: MS WORD ::   Chapters: 1-5 ::   Pages: 65 ::   Attributes: Questionnaire, Data Analysis,Abstract  ::   266 engagements

CHAPTER ONE INTRODUCTION 1.1 BACKGROUND TO THE STUDY Abandoned projects and construction failure including construction projects and other civil engineering infrastructure development project like...Continue reading »

THE ASSESSMENT OF FACTORS AFFECTING CONTRACTORS TENDER FOR CONSTRUCTION PROJECT

 Format: MS WORD ::   Chapters: 1-5 ::   Pages: 69 ::   Attributes: Questionnaire, Data Analysis,Abstract  ::   202 engagements

CHAPTER ONE INTRODUCTION 1.1 BACKGROUND OF THE STUDY Shash (1993) explains that a construction company can either negotiate with the client or use a competitive tendering process to obtain a contra...Continue reading »

INVESIGATION INTO THE DESIGN ERRORS AND ITS IMPACT ON INITIAL COST OF CONSTRUCTION PROJECT

 Format: MS WORD ::   Chapters: 1-5 ::   Pages: 111 ::   Attributes: Questionnaire, Data Analysis,Abstract  ::   149 engagements

CHAPTER ONE INTRODUCTION 1.1 BACKGROUND OF THE STUDY When asked to define "design error," not all disciplines in the construction process agree on a common definition. Depending on which ...Continue reading »

IMPACT OF COST CONTROL TECHNIQUES ON CONSTRUCTION PROJECT DELIVERY IN NIGERIA

 Format: MS WORD ::   Chapters: 1-5 ::   Pages: 86 ::   Attributes: Questionnaire, Data Analysis,Abstract  ::   211 engagements

CHAPTER ONE INTRODUCTION 1.1 BACKGROUND OF THE STUDY It is a known fact that the Nigerian construction industry continues to occupy an important position in the nation’s economy even though i...Continue reading »

A GEOPHYSICAL INVESTIGATION USING SEISMIC REFRACTION METHOD TO DETERMINE THE CAUSE(S) OF ROAD FAILURE

 Format: MS WORD ::   Chapters: 1-5 ::   Pages: 121 ::   Attributes: Abstract  ::   256 engagements

CHAPTER ONE MEANING AND BASIC APPLICATION OF GEOPHYSICS 1.1 INTRODUCTION It is to be noted that the geophysical method of prospecting and delineation of anomalous zone in the subsurface extend its w...Continue reading »

A STUDY INTO THE EFFECTS OF TIMELY DELIVERY OF CONSTRUCTION PROJECT ON ECONOMIC DEVELOPMENT OF NIGERIA

 Format: MS WORD ::   Chapters: 1-5 ::   Pages: 91 ::   Attributes: Questionnaire, Data Analysis,Abstract  ::   181 engagements

CHAPTER ONE INTRODUCTION 1.1 BACKGROUND OF THE STUDY Time impacts are inevitable on construction projects, primarily because of the uniqueness of each project and the limited resources of time and ...Continue reading »

What are looking for today?

WHAT OUR CUSTOMERS ARE SAYING:
  • 1. Abdoulrasheed Tapheeda from Taraba State University,Jalingo said "The Project Clue owe me a Tribute Respect, because of the nature of their work and delivery system. I recommend this site for any undergraduate due to the quality and fast delivery system of their work. Thanks".
    Rating: Excellent
  • 2. Sam Seyil from Federal Uni Agric. Markudi said "I had a wonderful experience using ProjectClue, they delivered not only on time, but the content had good quality. I recommend ProjectClue for any project research work.".
    Rating: Excellent
  • 3. Eval, Effa A. from University of Calabar (Unical) said "It was a wonderful experience using projectClue, it really helped me in carrying out a Term paper research NGP.".
    Rating: Good
  • 4. Abimbola Bisola from Obafemi Awolowo University said "Thanks a million times for giving me a quality research project. not only have i defended i was commended by my supervisor. You guys are the best; Project clue".
    Rating: Very Good
  • 5. Da Boss from Unilag said " projectclue.com is a blessing to Nigerian students. My job was delivered not only on time, they deliver high quality job. You guys exceeded my expectations".
    Rating: Very Good
  • 6. Denis Okalu from College of Education said "Great delivery. Una dey try wella!!!".
    Rating: Excellent